The ABS released the October 2026 monthly CPI on 25 November, and it came in higher than many expected. Prices rose 4.9 per cent over the 12 months to October, up from 4.3 per cent to September. Trimmed mean inflation, the measure that strips out the biggest moves, rose to 3.8 per cent from 3.6 per cent. Brisbane was a little below the national figure at 4.7 per cent.

Much of the coverage focused on electricity and fuel. For anyone preparing a development feasibility, I think the more useful line was further down the release: new dwelling prices rose 5.1 per cent over the year, driven by project home builders raising base prices to pass through higher labour and materials costs.

What the figures show

Housing was the largest contributor to annual inflation at 6.4 per cent. Electricity rose 25.2 per cent, largely because government rebates that lowered bills a year earlier are no longer in place.

New dwelling prices are the part that connects most directly to a construction budget. The ABS said they rose 0.8 per cent in October alone, after a flat September, and that builders in some cities cut discounts and raised base prices despite reports of subdued demand.

The Producer Price Indexes released on 30 October point the same way. Input prices to house construction rose 1.0 per cent in the September quarter and 3.9 per cent over the year. Brisbane recorded the largest quarterly rise of the capital cities at 1.6 per cent, driven by aluminium windows and doors.

Meanwhile the cash rate target is 4.85 per cent after the increase that took effect on 4 November, the fifth 0.25 point rise in 2026. The Reserve Bank's next decision is due on 8 December. I am not going to guess what it does. The point for a feasibility is that the margin has to work across a range of outcomes, not just the current one.

How a credit committee reads a feasibility

A feasibility that works on its base case tells a lender very little. What a credit committee wants to know is how much can go wrong before the project stops making a margin, and before the loan stops sitting comfortably inside the value of the security.

From my experience, the tests usually cover four things, first one at a time and then together:

**Construction cost.** What happens if the build costs more than the contract or the quantity surveyor's estimate? A fixed price contract helps, but variations, provisional sums and a builder under pressure can still move the number.

**End value.** What happens if sale prices or the completed value come in lower? This is where presales, valuation evidence and the depth of local buyer demand matter.

**Time.** What happens if approvals, the build or the sell down take longer? Every extra month adds interest, holding costs and, for a construction loan, the risk of reaching the facility expiry before the exit is in place.

**Interest rate.** What happens if the rate moves up during the term?

An illustrative stress test

Take an illustrative townhouse project with net sales revenue of $18.0 million and a total development cost of $15.0 million, with $9.0 million of that being construction cost. That gives a $3.0 million profit, a margin on cost of 20.0 per cent. These figures are arithmetic only, not a quote, a market rate or a real project.

- **Build cost up 5 per cent**, roughly in line with the annual rise in new dwelling prices: an extra $450,000, so profit falls to $2.55 million and the margin to about 16.5 per cent. - **End values down 5 per cent**: $900,000 less revenue, so profit falls to $2.1 million and the margin to 14.0 per cent. - **Six month delay**, with an average of $10 million drawn at an illustrative 9 per cent a year: about $450,000 of extra interest, a margin of about 16.5 per cent. - **Rate up 0.5 percentage points** for 18 months on the same $10 million average balance: about $75,000.

Combine the first three and profit falls from $3.0 million to $1.2 million on a cost of $15.9 million, a margin of about 7.5 per cent. That is still a profit, but there is not much left for anything else to go wrong.

In this example the rate rise is the smallest of the four. Cost, value and time do most of the damage, and they tend to arrive together, because a project that runs late often runs over budget and sells into a different market.

What I would have ready

If I were preparing a development facility in Brisbane, on the Gold Coast or elsewhere in South East Queensland, I would want the stress test done before the lender does it. That means an independent cost estimate with a realistic contingency, a fixed price contract with a builder that has the balance sheet to finish, sales or valuation evidence that does not rely on the best result in the street, a program with some slack, and an interest allowance sized for the delay case rather than the base case.

If the combined test leaves too little margin, the answer is usually more equity, a smaller first stage, more presales or a different capital stack, not a more optimistic spreadsheet.

I wrote more on how lenders size a facility in Loan to Cost and Loan to Value, on progress draws and capitalised interest in Construction Finance in Queensland, on building with few presales in No-Presale and Low-Presale Development Finance, and on mezzanine and preferred equity in Mezzanine and Preferred Equity in Australian Development Funding. For funding options, see development finance at Blended Ventures.

None of this is a recommendation to borrow, lend, invest or sell. Every site and project is different.

Sources

Australian Bureau of Statistics, CPI rose 4.9% in the year to October 2026 (media release, 25 Nov 2026)

Australian Bureau of Statistics, Consumer Price Index, Australia, October 2026

Australian Bureau of Statistics, Producer Price Indexes, Australia, September 2026 (30 Oct 2026)

Reserve Bank of Australia, Cash Rate Target

ABC News, Inflation rises more than expected to 4.9pc in year to October (25 Nov 2026)

Personal views, not financial advice.

Key questions

What did the October 2026 CPI show?

The ABS reported on 25 November 2026 that the CPI rose 4.9 per cent in the 12 months to October 2026, up from 4.3 per cent to September. Trimmed mean inflation was 3.8 per cent, up from 3.6 per cent. Housing was the largest contributor at 6.4 per cent, with electricity up 25.2 per cent and new dwelling prices up 5.1 per cent. Brisbane CPI rose 4.7 per cent over the year.

Why do new dwelling prices matter for developers?

The ABS said the 5.1 per cent rise in new dwelling prices was driven by project home builders raising base prices to pass through higher labour and materials costs. Separately, the ABS Producer Price Indexes showed input prices to house construction up 3.9 per cent over the year to the September quarter 2026, with Brisbane the largest quarterly rise of the capital cities at 1.6 per cent. Those are the same pressures that sit inside a development budget.

What is a feasibility stress test?

It is a set of what if scenarios a lender runs on a development feasibility. Typical tests move construction cost up, sale prices or end values down, extend the program, and lift the interest rate, both one at a time and together, to see whether the project still makes a margin and the loan still sits inside the value of the security.

Which stress usually hurts a feasibility most?

In the illustrative example in this article, a 5 per cent fall in end values and a six month delay each cost far more than a 0.5 percentage point rise in the interest rate. Every project is different, but time and value tend to matter more than the rate on its own.

Who is this relevant to?

Developers, commercial property owners and their advisers preparing a development feasibility or construction facility in Brisbane, the Gold Coast and wider South East Queensland. It is general commentary, not advice to borrow, lend, invest or sell.

Share this article

Share this article

Professional enquiries

The right
conversation
changes things.

For advisory engagements, commercial opportunities and international collaboration, get in touch directly.

Start a conversation