Building Work Is Up, New Home Sales Are Down: Presale and Settlement Risk for Developers

Back to Insights
Share this article

Two sets of figures released in November 2026 point in opposite directions, and I think the gap between them is where development risk sits for 2027.

On 25 November the ABS reported that residential building work rose 3.1 per cent in the September quarter to $30.4 billion, in seasonally adjusted chain volume terms, and was 9.3 per cent higher than a year earlier. That is the highest quarterly figure in the series the ABS shows back to 2018. A week earlier, on 17 November, the Housing Industry Association reported that new home sales in the three months to October were 27.3 per cent lower than a year earlier. Queensland had the largest fall of the five states surveyed, down 36.8 per cent.

So builders are busier than they have been in years, while the flow of new contracts behind them is drying up.

What the figures show

The ABS release covers work actually done in the quarter. Total construction work done rose 0.9 per cent to $88.2 billion, with building work up 2.4 per cent and engineering work down 0.9 per cent. Queensland was one of only two states where total construction work fell in the quarter, down 1.2 per cent, although it was still 2.6 per cent higher than a year earlier. These are preliminary estimates and the ABS will update them on 13 January 2027.

The HIA figures look forward. HIA said sales fell 19.3 per cent in October alone, that the slump came before the November rate increase, and that it expects the weakness to show up in building approvals in the March quarter 2027 and in detached home commencements from around the middle of 2027. On 25 November, after the October CPI came in at 4.9 per cent, HIA said commencements should stay relatively robust in the first half of 2027 because they reflect sales made earlier.

The cash rate target is 4.85 per cent and the Reserve Bank's next decision is due on 8 December. I am not going to guess what it does.

Why the gap matters for a development facility

A project under construction in late 2026 was usually sold, or at least priced, in a stronger market. Many of those projects will complete during 2027. At completion the presale buyers have to settle, and any unsold stock has to be sold into whatever the market looks like then.

That is why I think a lender looking at a townhouse or apartment project in Brisbane, on the Gold Coast or elsewhere in South East Queensland will spend less time on how many presales there are and more time on how many are likely to settle. The questions tend to be:

**Deposit and buyer quality.** How large are the deposits, and where are they held? Are the buyers owner occupiers or investors, local or offshore, and are any related to the developer?

**Contract price against current value.** If a buyer signed at a price above what a valuer would now support, their own lender may not fund the full amount at settlement.

**Sunset dates and program.** Is there enough time between practical completion and the sunset date for the build to run late without giving buyers a right to walk away?

**Concentration.** Are a handful of buyers holding a large share of the presales?

An illustrative example

Take an illustrative project of 24 townhouses with an average contract price of $850,000, or $20.4 million in total. The construction facility is $15.0 million fully drawn at completion, and 14 townhouses are presold for $11.9 million. To keep the arithmetic simple, I am ignoring selling costs and GST. These figures are arithmetic only, not a quote, a market rate or a real project.

- **Base case:** all 14 presales settle. $11.9 million repays debt, leaving $3.1 million against 10 unsold townhouses worth $8.5 million at the original price list, or about 36 per cent. - **Stress case:** 2 presales fail to settle, and the remaining stock sells 10 per cent below the original price list over an extra nine months. The 12 settlements repay $10.2 million, leaving $4.8 million against 12 townhouses now worth $765,000 each, or $9.18 million, about 52 per cent. Nine extra months on $4.8 million at an illustrative 9 per cent a year adds about $324,000 of interest.

In the stress case the loan is still covered, but the developer gives up about $1.02 million in price and about $324,000 in interest, roughly $1.34 million in total. That comes out of the margin, and it is the reason a lender sizes the facility on the settlement risk, not just the presale count.

What I would have ready

If I were carrying a project that completes in 2027, I would review the presale book now rather than at practical completion: deposit levels, buyer finance where it is known, contract prices against recent valuation evidence, and sunset dates against a realistic program. I would also have a plan for the unsold and failed stock, whether that is a longer sell down, a residual stock facility or more equity, before the construction loan reaches expiry.

I wrote more on building with few presales in No-Presale and Low-Presale Development Finance, on what happens after completion in Residual Stock Finance, on testing margin and time in Inflation at 4.9 Per Cent and How a Credit Committee Stress-Tests a Development Feasibility, and on how a facility is sized in Loan to Cost and Loan to Value. For funding options, see development finance at Blended Ventures.

None of this is a recommendation to borrow, lend, invest or sell. Every site and project is different.

Sources

Australian Bureau of Statistics, Construction Work Done, Australia, Preliminary, September 2026 (released 25 Nov 2026)

Housing Industry Association, New homes sales slump puts housing supply in 2027 under pressure (17 Nov 2026)

Housing Industry Association, Elevated inflation risks further constraining housing supply (25 Nov 2026)

Reserve Bank of Australia, Cash Rate Target

Personal views, not financial advice.

Key questions

What did the ABS construction figures released on 25 November 2026 show?

The ABS Construction Work Done, Australia, Preliminary release for the September quarter 2026 showed total construction work done up 0.9 per cent to $88.2 billion in seasonally adjusted chain volume terms. Residential building work rose 3.1 per cent in the quarter to $30.4 billion and was 9.3 per cent higher than a year earlier. Queensland total construction work done fell 1.2 per cent in the quarter but was 2.6 per cent higher over the year.

What has happened to new home sales?

The Housing Industry Association reported on 17 November 2026 that new home sales fell 19.3 per cent in October, and that sales in the three months to October were 27.3 per cent lower than a year earlier. Queensland had the largest fall of the five states surveyed, down 36.8 per cent over that period. HIA expects the slump to show up in building approvals data in the March quarter 2027.

Why does the gap between building work and sales matter for developers?

Work under way in late 2026 was largely sold or committed when conditions were stronger. Projects that complete in 2027 may settle and sell their remaining stock into a market with fewer buyers, so a lender will look closely at how many presales are likely to settle and what happens to the debt if some do not.

What is settlement risk on a presale?

It is the risk that a buyer who signed an off the plan contract does not complete on the agreed terms at settlement, for example because their own finance falls short or the property values below the contract price. Each failed settlement leaves the developer with another unsold dwelling and more debt to clear.

Who is this relevant to?

Developers, commercial property owners and their advisers preparing or carrying a development facility in Brisbane, the Gold Coast and wider South East Queensland. It is general commentary, not advice to borrow, lend, invest or sell.

Share this article

Share this article

Professional enquiries

The right
conversation
changes things.

For advisory engagements, commercial opportunities and international collaboration, get in touch directly.

Start a conversation